Construction Update as of July 21, 2010 The project has entered the final construction phase, grow in. Duininck Bros. Construction has completed their work and will be leaving the site this week. At this time, the new holes look great. The golf maintenance staff has completed seeding all the greens, tee boxes, fairways and rough areas. Staff is irrigating as needed and hoping for favorable weather for the grow in phase of the project. Sod has been placed to allow hole #4 to play as a short hole. Staff anticipates being able to open hole #4 next week. This will allow for 16 holes to be available for play instead for 15 holes. Stay tuned for more information. Construction Update as of July 9, 2010 This week, the irrigation is almost complete. The contractor is working on the final wiring. To date, the greens have been seeded and the cart paths have been completed. At this time, the contractor is working on the pond. The Architect will be onsite next week to review the progress of the re-construction on holes 2, 3 & 4. Staff estimates the project to be completed in a week. Stay tuned for further weekly updates. Check out the current construction photos below.
Construction Update as of June 3, 2010 "As conditions allow" this is our proposed schedule to complete holes 2, 3 & 4:
Stay tuned for further weekly updates. Check out the current construction photos below.
Construction Update as of May 27, 2010 This week, the Architect came and reviewed the progress of the re-construction on holes 2, 3 & 4. Most of the black dirt should be in place by the first week in June and the new greens will be seeded by June 15th. Stay tuned for further weekly updates. Construction Update as of May 13, 2010 This week, the Architect came and reviewed the progress of the re-construction on holes 2, 3 & 4. Also, the new greens and tees were staked. Next week, Duininck expects to complete the digging of the pond and moving material. Stay tuned for further weekly updates. Construction Update as of May 6, 2010 At this time, Duininck continues to work through the wet weather. Some of the items accomplished so far are: cutting down grade on upper 2 fairway, raising area of future green, rough shaping for 3 tee, elevating site of new 3 green. Tree stumps have been removed. Asphalt paths have been removed. Today and immediate future work is the digging of the pond and moving this material to raise new 4 fairway. Duininck plans to haul out the old asphalt next week, and the pond might be completely dug by the end of next week. Stay tuned for further weekly updates. Check out the current construction photos below.
Edgewood Flood Mitigation Phase IThe Fargo Park Board approved Option B-1A on Tuesday, September 8th, 2009 at the park board meeting. Click here to view Option B-1A. This Option relocates the tees for hole #2, has a new green constructed for hole #2, hole #3 becomes a par 3 with new tee boxes constructed up in the trees by the entrance road and reuses the green on #2 (proposed) which would now become green #3. New tee boxes would be constructed for hole #4 and the existing green for hole #4 would be used and the existing #3 green would be abandoned. Need a gift? Pick up a Fargo Park District Gift Card Today!
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||
| |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||
| |
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||